Currently looking at the Staverton Primary project

A new two classroom extension with associated support accommodation providing 200m2 of additional teaching space.

The construction of this new block was undertaken within the live school environment and in order to mitigate the risks associated with this our designers specified a frame constructed using cross laminated timber panels which was manufactured off site and erected on site over a 9 day period.

The timber of the frame is finished with a fireproof varnish and the exterior elevations clad in coloured Trespa cladding panels, again minimising the erection time required on site.